Projects

We believe our work speaks for itself

On Going Tower Line Constructions

Project Client / Contact Person Amount Commencement Date Percentage of Completion
Polpitiya-Hambantota 220kV transmission line project (Ongoing) China National Cable
Mr. Alex- 0766377361
32.2 Mil 2020.12.10 70%
Construction of 132kV transmission line from Thulhiriya to Weyangoda (Ongoing) CEYLAX Engineering (Pvt) Ltd. Mr. Lahiru – 0777320924 10.5 Mil 2021.04.08 50%
Construction of 33kV four circuit lynx tower line from Kesbewa GSS to Welmilla Gantry, (Stage 01 - Kesbewa GSS to Polgasowita Junction; 01km). Erection of foundation & towers - 04 tower locations Ceylon Electricity Board Eng. Mr. Sampath – 0714908913 35.8 Mil 2021.06.25 50%
Construction of 05 nos. of concrete pad and chimney foundations for towers of 132kV transmission line from Athurugiriya GSS to Kolonnawa GSS Ceylon Electricity Board Eng. Mr. Manjula- 0713685673 12.4 Mil 2021.09.01 80%
Contract for foundation & erection of steel towers in 1.85km, 33kV D/C Lynx tower line from Bemmulla to Magalegoda Ceylon Electricity Board Mr. Haputhanthri- 0718693265 11.15 Mil 2021.07.19 20%

Experience in Transmission Tower Line Construction

Project Client Amount Duration
Construction of concrete pad chimney foundation for 1 no. of 132 kV, TDL + 12 tower at Malabe Ceylon Electricity Board 0.6 Mil 1 Month
Uma Oya Multipurpose Development Project 132 kV, single zebra transmission tower line CEYLAX Engineering (Pvt) Ltd. 22.5 Mil 12 Months
Habarana – Veyangoda 220kV DC line CEYLAX Engineering (Pvt) Ltd. 47.4 Mil 17 Months
Construction of 132 kV transmission line from Galle to Ambalangoda KEC International (Pvt) Ltd. 11.5 Mil 6 Months
Construction of 132 kV DC transmission line Kalpataru Power Transmission Limited 3.7 Mil 3 Months

Experience in Distribution Tower Line Construction

Project Client Amount Duration
Contract for foundation & erection of steel towers in 0.175km, 33kV DC lynx tower line crossing at Rathmalvita (TDM+6 – 02 Nos) Ceylon Electricity Board 3.94Mil 1 Month
Foundation & erection of an additional sl+3 double pole structure for Madurupitiya – Loluwagoda 33kv DC lynx tower line Ceylon Electricity Board 0.5 Mil 1 Month
Conversion of S/C racoon tower line to D/C lynx tower line from Wewelwatta GSS to Durekkanda Gantry (5km) Ceylon Electricity Board 20.5 Mil 9 Months
Construction of tower foundations and tower erection works at four circuit zebra, lynx tower line from Kerawalapitiya GSS to Mabola-stage -I Ceylon Electricity Board/Geo Engineering Technologies (Pvt) Ltd. 11.5 Mil 3 Months
Construction of tower foundations and tower erection works at four circuit zebra, lynx tower line from Kerawalapitiya GSS to Mabola stage 0I Ceylon Electricity Board/Geo Engineering Technologies (Pvt) Ltd. 6.5 Mil 3 Months
Construction of tower foundations and tower erection works at double circuit lynx tower line from Kerawalapitiya GSS to Mabola PSS stage 03 (650m) Ceylon Electricity Board/Geo Engineering Technologies (Pvt) Ltd. 13 Mil 3 Months
Construction of 4 nos. 33kV lattice tower with pile foundation at Yakkabedda, Matara Ceylon Electricity Board/Geo Engineering Technologies (Pvt) Ltd. 1.5 Mil 2 Months
Construction of 33kV transmission line from Jambugahapitiya to Katugasthota Sierra Construction (Pvt) Ltd. 3.8 Mil 3 Months

Experience in Telecommunication Tower Line Construction

Project Client Amount Duration
Construction of Dialog telecommunication tower TWF-628 – Dalukana Huawei/Tantri (Pvt) Ltd. 3.5 Mil 2 Months
Construction of telecommunication tower at Norochcholi Ceylon Electricity Board 3.5 Mil 2 Months

Experience in Civil Construction

Project Client Amount Duration
Proposed oil drum storage facility construction Chevron Lubricant PLC 6.5 Mil 3 Months
Steel structure for boilers Chevron Lubricant PLC 5.5 Mil 1 Months
Proposed fence and gate construction Department of Meteorology – Sri Lanka 4 Mil 2 Months
Thihagagoda Dhuwa Ela irrigation rehabilitation project Southern Provincial Irrigation Department 5.5 Mil 4 Months
Construction of steel building Nisura Enterprises 10.5 Mil 3 Months
Construction of steel building Divara Tea Factory 16.4 Mil 6 Months
Construction of steel building Dakma Education 12.1 Mil 3 Months
Construction of residence building Mrs. Dilini Pemachandra 10.8 Mil 12 Months
Construction of residence building Mr Susantha Wanniarachchi 10.2 Mil 8 Months
Construction of residence building Mrs. Amali Niranga 16 Mil 12 Months
Construction of residence building Ms. R.S.P.Dharmarathne 7 Mil 6 Months
Construction of resort building Mr. B.G.Danidu Thisun 10.4 Mil 9 Months
Construction of resort building Surf Bay Villa 18 Mil 15 Months
Construction of steel building Alta Vision (Pvt) Ltd. 14.5 Mil 9 Months